Independent travel intelligence. Sources cited on every guide. LatestTangier Al Atlas Trains Disrupted Through Nov. 17 for Station WorksBookeasy Hack Shuts Park Bookings in Queensland and VictoriaMet Office Snow Warning: Delays for Northern England TuesdayPittsburgh Sister Bridges Closed One a Day, Nov. 16-18

Vestfoldbanen Closure: RE11 Bus Transfers Begin October 12

Vestfoldbanen RE11 bus transfers start October 12 between Drammen and Stokke. Check direct buses, earlier southern trains and new Horten boarding.

ShareEmailWhatsAppLinkedInXFacebook
Archival Vestfoldbanen track work near Tonsberg on July 27 2023, not the October 2026 closure

Vestfoldbanen passengers face a new bus leg from Monday, October 12, 2026, when Norway’s RE11 rail service is interrupted between Drammen and Stokke. Vy’s passenger advisory sets out replacement buses between Asker and Stokke, direct buses to Tønsberg and Horten, and changed departures on the remaining Stokke to Skien train section. The disruption continues until November 22 under the published plan.

The practical change is not simply a longer version of your usual train ride. Check which bus serves your destination and whether an onward train departs earlier than normal. Several southern RE11 departures move by as much as 30 minutes, and those trains use fewer carriages. A saved timetable can therefore be wrong even for a section where trains still run.

Image context: Vestfoldbanen track work near Tønsberg on July 27, 2023. This archival image does not depict the October 2026 work.
At a Glance
  • Closed rail section: Drammen to Stokke on RE11.
  • Work window: October 12 at 02:00 to November 22 at 04:00, local time, according to Bane NOR.
  • Main replacement: Buses between Asker/Drammen and Stokke.
  • Direct options: Asker to Tønsberg and Asker to new Horten station.
  • Southern trains: Stokke to Skien continues, with several earlier departures and fewer carriages.

Choose the bus for your actual station

Vy lists replacement buses from or to Asker/Drammen serving Drammen, Sande, Holmestrand and Stokke during the work. It also provides separate direct buses between Asker and Tønsberg and between Asker and Horten. These are different journey options, not a promise that every bus stops at every station.

The operator advertises departures up to every ten minutes in rush traffic for the direct services. That is a peak-period description, not an all-day frequency guarantee. Check the departure offered for your date and time before assuming a ten-minute wait, particularly outside commuting periods or at a different boarding station.

Vy says customer guides will be present at the largest stations to help passengers find the correct bus. The advisory does not provide one universal boarding bay or journey duration. Use the live journey search and signs at the relevant station rather than treating a general replacement-bus notice as a complete individual itinerary.

Check earlier trains south of Stokke

Trains continue between Stokke and Skien, but several departures receive new times and leave up to 30 minutes earlier than usual. The same services have fewer carriages. This is not an announcement that every departure moves by exactly half an hour or that a particular seat will be unavailable.

For a bus to train connection, build the trip around the revised onward departure. Arriving at a station for the old train time could be too late. Conversely, an earlier scheduled train does not establish how long the bus leg takes; those are separate parts of the journey that need checking together.

Vy recommends its current journey search before travel. Check both directions if you are returning the same day, and keep the actual departure details available rather than relying on a familiar weekday pattern.

Horten bus access replaces Skoppum

In its October 2 project update, infrastructure manager Bane NOR says Skoppum station permanently closes from October 12. Passengers traveling to or from Horten can use replacement buses via the new Horten station during the work period.

That bus access and the later start of rail service are different milestones. Bane NOR plans to put the new railway into ordinary operation on November 22. Do not interpret the availability of buses at new Horten as evidence that passenger trains already serve it.

If a saved app favorite or hotel instruction still points to Skoppum, check the current Horten journey before departure. Vy also advises updating saved station information for the new Horten service after the work. The useful check now is the actual bus boarding location, not simply waiting until the rail reopening date to reconsider the old station name.

Testing does not mean passenger trains have returned

Bane NOR’s Drammen to Stokke traffic entry sets the closure from October 12 at 02:00 until November 22 at 04:00. The work connects the new Nykirke to Barkåker double track and includes other tasks along the closed corridor.

The largest construction activities are scheduled through November 4. Energization, technical testing and train test runs follow before ordinary operation starts. Vy warns that empty trains may be visible on the tracks while the section is still closed to passengers.

Seeing a train is therefore not a reason to abandon the replacement-bus plan. For trips near the end of the window, check the actual published passenger departure and any updated notice. The stated work boundary is not a substitute for a confirmed booking.

Journey Decision Matrix
Your trip Use this plan
Across Drammen to Stokke Check Vy’s Asker/Drammen to Stokke replacement buses and your required stop.
Asker to Tønsberg or Horten Check the direct bus. Peak intervals are not an all-day guarantee.
Stokke to Skien by train Check the revised departure; several trains leave up to 30 minutes earlier.
A saved Skoppum itinerary Check new Horten bus access and the current boarding location.
What This Means for Travelers

Allow extra journey time without assuming a fixed delay figure. Check the bus leg, onward train and return trip separately, then use the current planner to confirm the connection.

Frequently Asked Questions

When does the RE11 interruption begin?

Bane NOR lists October 12, 2026, at 02:00 for the Drammen to Stokke closure. The published end is November 22 at 04:00, local time.

Are all southern RE11 trains canceled?

No. Stokke to Skien trains continue, with several earlier departures and fewer carriages. The closed Drammen to Stokke section has replacement buses.

Do direct buses run every ten minutes all day?

No such all-day guarantee is given. Vy describes intervals up to ten minutes during rush traffic. Check your specific departure.

Image Credits

Table of Contents

The weekly brief

One calm email. The week's plan.

Park hours, crowd outlook, fare moves, and what changed, plus first word as we open new destinations. No noise, just the planning signal.

Free. Unsubscribe anytime. We never sell your address.