Newcastle City Council and Gateshead Council closed the Tyne Bridge to every vehicle, pedestrian and cyclist at 11pm on Friday, October 23, 2026, for ten full days until 5am on Monday, November 2. The councils say the complete closure lets specialist teams install an overhead protection deck above the carriageway before restoration moves to the main steel arch in early 2027, as reported by Travel And Tour World.
Anyone crossing between Newcastle and Gateshead through November 2 should reroute now and allow much more time, because the signed detours will push extra traffic onto surrounding bridges and tunnels. Visitors basing in the city can still enjoy both riverfronts by planning around the closure with our Newcastle Itinerary 2026, which groups the key Quayside sights within easy walking blocks once you pick the right crossing.
- Closure: Tyne Bridge fully closed 11pm October 23 to 5am November 2, 2026, with no vehicle, bike or foot access.
- Reason: Install scaffolding and a protection deck so the 2027 main arch restoration can proceed while the bridge stays open later.
- Daily impact: About 24,000 vehicles a day must use other Tyne crossings, with heavy congestion expected across Tyneside.
- Overnight follow on: Weeknight vehicle closures run 8pm to 6am Monday to Friday through November to finish the scaffolding work.
- Visitor advice: Use public transport where possible, avoid central Newcastle and Gateshead by car, and choose step free High Level Bridge on foot.
Tyne Bridge October 23 Closure Dates and Hours
The full closure covers ten calendar days across the October half term break, a window the councils chose because traffic is lighter when schools are closed. Newcastle City Council lists the start as 11pm on Friday, October 23 and the reopening as 5am on Monday, November 2, with all times local United Kingdom time.
Daytime access is scheduled to resume on November 2 after the scaffold deck structure is secure. A separate programme of weeknight vehicle closures continues through November, Monday to Friday from 8pm until 6am, to complete the remaining scaffolding work, while pedestrians and cyclists keep access during that overnight phase, according to Spark Sunderland.
Newcastle Detour Routes for Drivers During November 2 Works
Drivers should stay on major trunk roads and avoid driving through the centres of Newcastle and Gateshead, because signed diversions will already be loading the alternative crossings. The councils point motorists to the A1, the A19 Tyne Tunnel and Scotswood Bridge, with diversions marked on approach roads.
The A19 Tyne Tunnel charges £2.60 per journey for the quoted car trip, a cost local resident Cher Ridley highlighted to Spark Sunderland alongside extra fuel and longer drive times. She said the tunnel can already take up to 20 minutes at peak times and warned that displaced bridge traffic will make queues worse, so budget both money and schedule buffer.
Expect the Quayside roads, Swing Bridge approaches and Redheugh Bridge approaches to run busier than usual. The councils say the wider programme remains on schedule to finish before the bridge centenary in October 2028.
Tyne Pedestrian and Cycle Crossings Open During Closure
Walking and cycling across the Tyne Bridge itself is not possible during the ten day full closure. People on foot or by bike can instead use the High Level Bridge, the Swing Bridge or the Gateshead Millennium Bridge to move between Newcastle and Gateshead.
Route choice matters for luggage, strollers and mobility needs. Project guidance notes the High Level Bridge route is generally level, while approaches through the Quayside to the other crossings involve gradients that feel longer with bags. If you are sampling both banks between meals, our Where to Eat in Newcastle upon Tyne groups five stops by area so you can eat on the side where you already are.
Tyne and Wear Bus and Metro Changes for November 2 Travel
Stagecoach and Go North East are the main bus operators affected, with Arriva service X12 also diverted. Go North East says services 22, 28, 28B, 29, 58, X1, X1A, X1B and X21 terminate at Gateshead Interchange during the works, so passengers continuing to Newcastle must change buses there.
Check boarding points before you travel, because several city centre stops move and some through journeys now need a connection. Separate rail disruption adds to the same travel window, with a nine day Metro closure planned between Monkseaton and St James, plus wind related bus diversions noted in the current travel guidance.
Why the Tyne Bridge Arch Restoration Needs Scaffolding
Work on the multi million pound restoration began in 2024 and has focused for two years on the lower sections and east side parapets. Council leader Cllr Colin Ferguson said significant progress and a major transformation have taken place down low, and the programme now moves to the main bridge arch, the centrepiece and most visually prominent phase.
Engineers must fit extensive scaffolding above the carriageway before arch work starts in early 2027. Doing that fitting under a full ten day closure gives safe and uninterrupted access, saves time overall and reduces longer term disruption compared with months of partial closures. The Tyne Bridge is a Grade II star listed structure, and the councils frame the work as preserving an icon for future generations.
Gateshead Council leader Cllr Nick Allan urged patience across Tyneside during the ten days, saying everyone shares the objective of seeing restoration completed in 2028. Newcastle and Gateshead remain open for business throughout, but the councils ask visitors to plan ahead, allow more time and use public transport where possible.
| If you… | What to do |
|---|---|
| Drive between Newcastle and Gateshead through November 2 | Use the A1, A19 Tyne Tunnel or Scotswood Bridge, avoid city centres, and allow 30 minutes extra plus tunnel fare. |
| Walk or cycle between the Quaysides through November 2 | Cross by High Level Bridge for the most level route, or by Swing Bridge or Gateshead Millennium Bridge, and expect gradients on Quayside approaches. |
| Ride Go North East buses to Newcastle through November 2 | Ride to Gateshead Interchange on 22, 28, 28B, 29, 58, X1, X1A, X1B or X21, then change for Newcastle and recheck your boarding stop. |
| Travel late at night in November after the bridge reopens | Expect weeknight vehicle closures 8pm to 6am Monday to Friday, when drivers divert but pedestrians and cyclists can still cross. |
October 23 at 11pm is the first gate. From that hour the Tyne Bridge admits no cars, buses, bikes or pedestrians, so switch every cross river plan to the A1, Tyne Tunnel, Scotswood Bridge, High Level Bridge, Swing Bridge or Millennium Bridge.
November 2 at 5am is the second gate. Daytime vehicle, bike and foot access is scheduled to resume then, but recheck the councils before a tight connection because engineering works can shift by hours.
November weeknights are the third gate. After the full reopening, Monday to Friday 8pm to 6am vehicle closures continue for scaffolding, so book late arrivals by Metro, rail or on the same side as your hotel.
Is the Tyne Bridge open to pedestrians during the October closure?
No. From 11pm October 23 to 5am November 2 there is no pedestrian or cyclist access on the Tyne Bridge itself. Use High Level Bridge, Swing Bridge or Gateshead Millennium Bridge instead.
How much extra time should drivers allow in Newcastle this week?
Allow significantly longer than usual and avoid central Newcastle and Gateshead by car. The closure displaces about 24,000 vehicles a day, and the Tyne Tunnel alone can take up to 20 minutes at peak times before the extra load.
Do buses still run between Gateshead and Newcastle?
Yes, with diversions. Go North East services including 22, 28, 28B, 29, 58, X1 series and X21 terminate at Gateshead Interchange, where you change for Newcastle. Stagecoach and Arriva X12 also divert, so confirm your stop.
Will night travel still be affected after November 2?
Yes. Weeknight vehicle closures run 8pm to 6am Monday to Friday through November to finish scaffolding. Pedestrians and cyclists can still cross during those overnight works.