Most of Oslo’s metro, the T-bane, will close from Thursday, November 19, to Sunday, November 22, 2026, while a new signalling system is tested, Oslo transit authority Ruter said on September 10. No metro trains will run through the city center, and Ruter’s message to riders is blunt: do not travel unless you have to.
The test requires whole sections of track without passengers, VG reported in May when metro operator Sporveien first announced a four-day November closure. T-bane director Christian Skaug told the paper that, to his knowledge, closing central parts of the network had never happened before.
- Dates: Thursday, Nov. 19, to Sunday, Nov. 22, 2026.
- Closed: most of the T-bane, including the city center.
- Still running: outer parts of lines 1, 2 and 3.
- Instead: trams Majorstuen to Jernbanetorget, plus buses.
- Advice: travel only if necessary; walk or cycle if you can.
Which Lines Still Run
Ruter says only three outer sections will have metro trains. Line 1 runs only between Frognerseteren and Frøen. Line 2 runs only between Østerås and Makrellbekken. Line 3 runs only between Kolsås and Ullernåsen. The rest of the network, including the central stations, has no metro service, and Ruter says details may still change before the closure.
Between Frøen and Majorstuen, Ruter offers special or booked transport for customers who need extra support. Replacement buses run between Hovseter and Majorstuen for line 2 riders, and between Åsjordet and Majorstuen for line 3 riders, according to Ruter.
Trams and Buses Through the Center
To cross the city, Ruter is running a tram replacement between Majorstuen and Jernbanetorget, the stop by Oslo Central Station, and adding capacity on bus line 19x. Elsewhere, parts of the network without their own replacement are covered by reinforced regular public transport. Ruter’s acting chief executive, Sondre Eftedal Blom, said the extra buses and trams do not replace the metro, and Ruter advises walking or cycling where possible.
For visitors, that means trips that normally take a few minutes underground between the center and Majorstuen, or out to the eastern suburbs, will take longer on trams and buses. If your hotel is near a T-bane station, check Ruter’s travel planner for the exact replacement before you set out on those four days, and allow extra time to reach Oslo Central Station for airport trains.
Why the Metro Is Closing
Ruter says the signalling system has not been replaced since the mid-1960s. The new system must be tested on whole sections of track, and for safety reasons the tests must run without passengers. Ruter says the work will also allow more departures and let trains run on the planned Fornebu line, and that this is the first of several closures planned for 2027.
VG reported that the new system, known as CBTC, will be tested on the Ring line, the central tunnel and the Sognsvann line, and that central parts of the network are due to run on it by autumn 2027. Project director Jon Are Pettersen told the paper the testing is absolutely necessary to keep the T-bane safe. Birte Sjule, chief executive of Sporveien, said in Ruter’s release that the metro has never had a larger closure than this one.
Planning Your Visit
The closure runs from a Thursday through a Sunday, so it catches both commuters and weekend visitors. Ruter says it is sending letters with advice to schools, hospitals and other organizations. Marit Vea, Oslo’s city councillor for environment and transport, said the city is switching the entire signalling system to a new, modern one. If your trip can move by a few days, avoiding November 19 to 22 is the simplest fix.
Scale explains the warning. VG reported that the T-bane carries several hundred thousand trips a day, and Ruter says the extra trams and buses cannot replace that capacity, which is why it asks people to walk, cycle or skip trips they do not need to make.
| If you are | What to do |
|---|---|
| Crossing central Oslo | Take the replacement tram via Majorstuen. |
| Heading to Holmenkollen | Use line 1 from Frøen. |
| Staying on line 2 or 3 | Use the buses to Majorstuen. |
| Flexible on dates | Avoid Nov. 19 to 22. |
No metro. City center and most lines, Nov. 19 to 22.
Outer sections. Parts of lines 1, 2 and 3 run.
Replacement. Trams, buses and line 19x.
Is the Oslo T-bane closed in November 2026?
Most of it is closed from November 19 to 22, 2026, including the city center.
Which T-bane lines run during the closure?
Only outer parts of lines 1, 2 and 3, Ruter says.
How do I get across central Oslo?
A replacement tram runs between Majorstuen and Jernbanetorget, and bus 19x has extra capacity.
Why is the T-bane closing?
A new signalling system must be tested on empty track, replacing one from the 1960s.
Image Credits
- Lead Photo
Holmenkollen stasjon 5 · Alasdair McLellan · CC BY-SA 3.0 · edited