Independent travel intelligence. Sources cited on every guide. LatestLondon Museum Opens November 28 at Smithfield With Free GalleriesVietjet S$86 Singapore Vietnam Sale Ends October 10eVisas.com Expands Visa Help to 29 Destinations for US Travelers on October 8Isle of Man Steam Packet Company Cuts November Ferries

Heathrow Third Runway Could Slip to 2039, Four Years Late

ShareEmailWhatsAppLinkedInXFacebook
Aerial view of Heathrow Airport's two runways and terminals west of London

Heathrow Airport has warned that its planned third runway may not open until 2039, up to four years later than the government’s hoped-for 2035, because of planning and regulatory hurdles, the BBC reports. The airport said on Saturday 26 September 2026 that it hopes to win planning permission by 2029 and then open the runway “within a decade”, which it describes as its core scenario all along.

For travellers, the delay means Heathrow stays a two runway airport with its flights capped at 480,000 a year well into the 2030s, so the slot squeeze that shapes fares and new routes at Britain’s busiest airport is set to last longer. It also puts fresh focus on how passengers get to the airport; The Guardian reports that Transport for London (TfL) wants the future of the Heathrow Express reviewed.

At a Glance
  • New timeline: planning permission hoped for by 2029, runway open within a decade, possibly 2039.
  • Government target: 2035, which the Department for Transport says was always ambitious.
  • Cost: about £33bn for the runway within a wider £49bn airport modernisation.
  • Capacity: flights capped at 480,000 a year now; up to 720,000 with a third runway.
  • Getting there: TfL has questioned the Heathrow Express; Elizabeth line trains to Terminal 5 are due to double next year.

Why Heathrow Says the Runway Could Slip

Heathrow says the 2035 deadline is increasingly difficult to meet without further steps to simplify the planning process. A draft planning framework for the expansion was published for consultation in June; once finalised, it needs a parliamentary vote, which could reportedly slip to 2027, the BBC says. The Guardian reports that airport bosses have told ministers the runway will not now be operational until 2039.

The Department for Transport said the timeline “has always been ambitious” and that there is currently no live planning application for a third runway. A Heathrow spokesperson said: “It’s right that ambitious targets were set; the sooner expansion begins, the sooner the whole UK will benefit.”

720,000 Flights a Year With a Third Runway

Heathrow serves more than 80 million travellers a year across four passenger terminals and two runways. A third runway would let flights rise from the current cap of 480,000 a year to as many as 720,000, nearly 2,000 a day on average. The plan would mean demolishing hundreds of homes, diverting rivers and rerouting the M25 through a tunnel under the new runway between junctions 14 and 15, according to the BBC.

Heathrow says the privately financed project would create at least 108,000 jobs. It faces opposition from environmental campaigners, local residents and London mayor Sadiq Khan, and the government’s climate advisers have said it should only go ahead if airlines pay for cleaner flying, which could push up fares.

Heathrow Express Under Review

Under the expansion plan, 100,000 to 200,000 more passengers a day would eventually travel to or from Heathrow, The Guardian reports, which makes rail access a pressing question. TfL told MPs this month that the Heathrow Express was “taking up valuable paths that aren’t actually well used”, and has said its future is worth reviewing in the context of capacity on the Great Western main line.

The Heathrow Express charges £26 for a one way trip of 15 to 21 minutes to Paddington and carried 4.5 million passengers last year, less than 6 percent of the airport’s air passengers, according to The Guardian. The Elizabeth line charges £15.50 to its central London stations, but only two trains an hour currently serve Terminal 5, which handles about 40 percent of Heathrow’s passengers. That frequency is due to double next year.

Heathrow Trips in the Meantime

Nothing changes at Heathrow in the short term: the airport keeps its two runways and current terminals. Over the coming decade, the tight slot supply means airlines will keep competing for a fixed number of flights, and new routes at Heathrow will depend largely on airlines swapping or buying slots rather than on added capacity. For getting into London, compare the Heathrow Express with the Elizabeth line on price and total journey time to your final stop, especially if you are going beyond Paddington.

What to Do
If you are What it means
Flying from Heathrow this year or next No change: two runways and existing terminals.
Heading to the City or Canary Wharf from Terminal 5 Check Elizabeth line times; only two trains an hour until frequency doubles next year.
Going to Paddington quickly The Heathrow Express is fastest at £26; the Elizabeth line costs £15.50.
Watching for new Heathrow routes Expect limited growth while flights stay capped at 480,000 a year.
Travel Impact

Capacity squeeze lasts longer. A third runway may not open until 2039.

No short term change. Heathrow operates as today with two runways.

Rail access in focus. TfL wants the Heathrow Express reviewed as Elizabeth line service to Terminal 5 grows.

Frequently Asked

When will Heathrow’s third runway open?

Heathrow now says it hopes for planning permission by 2029 and to open the runway within a decade, which could mean 2039, four years after the government’s 2035 target.

How many flights would a third runway allow?

Up to 720,000 a year, compared with the current cap of 480,000, or nearly 2,000 a day on average.

Is the Heathrow Express closing?

No decision has been made. TfL has said its future is worth reviewing as part of planning for rail capacity to the airport.

Table of Contents

The weekly brief

One calm email. The week's plan.

Park hours, crowd outlook, fare moves, and what changed, plus first word as we open new destinations. No noise, just the planning signal.

Free. Unsubscribe anytime. We never sell your address.