Easton Airport will close Runway 4/22 at 8:00 AM on Thursday, October 29, 2026, and keep it closed until 8:00 AM on Friday, December 18, 2026, to build the new Runway 4/22. The airport published the schedule in its Easton Airport public notice dated October 23, 2026, after more than 20 years of planning for the project.
Pilots and airport visitors should plan around the closure now because the main runway will be unavailable for seven weeks except for announced festival and holiday openings. Our airline and airport operations guides explain how to check runway status before a flight, and this closure is a clear case for that routine.
Runway 15/33 will remain available for normal operations during the closure, according to both the airport and regional coverage of the update. Travelers who use Easton Airport in Talbot County, Maryland, should confirm which runway applies to each arrival and departure and allow extra time for revised traffic patterns.
- Closure: Runway 4/22 closed 8:00 AM October 29, 2026, to 8:00 AM December 18, 2026.
- Place: Easton Airport in Easton, Talbot County, Maryland.
- Open runway: Runway 15/33 remains available for normal operations.
- Planned reopenings: Waterfowl Festival November 13 to 15 and Thanksgiving weekend, with exact times announced at least 7 days ahead.
- Next step: Check NOTAMs before every flight and plan for further Runway 4/22 closures through 2027.
Runway 4/22 Closure Dates and Times
The closure begins at 0800 local time on October 29 and ends at 0800 local time on December 18. The airport set the same morning hour for both the start and the return to service, which makes the seven week interval easy to place on a flight calendar.
The work supports construction of the new Runway 4/22, a project the airport describes as the result of more than 20 years of planning, dedication and perseverance. Pilots should treat the published times as local airport time and verify them in the current NOTAM for Easton Airport before departure.
Waterfowl Festival and Thanksgiving Openings
Runway 4/22 will open temporarily for the Waterfowl Festival from November 13 to November 15 and for Thanksgiving weekend. The airport has not fixed the exact hours for those openings yet, and it says specific dates and times will be coordinated and announced at least 7 days in advance.
Visitors who plan to fly in for the festival should therefore watch for a second announcement in early November rather than assuming the runway is open all weekend. The 7 day coordination promise is the booking gate for that trip, so no festival flight plan is complete until that update appears.
Runway 15/33 Stays Open for Normal Operations
During the Runway 4/22 closure, Runway 15/33 will remain available for normal operations. The airport states that point directly in the October 23 notice, and the regional report repeats it as the central operating fact for the construction period.
Pilots should brief the 15/33 layout, check crosswind and performance limits for their aircraft, and confirm parking and taxi routing with the airport. Passengers who meet arriving aircraft should confirm which runway and traffic pattern are in use on the day of travel.
NOTAM Checks and Seven Day Coordination
The airport directs pilots to check NOTAMs for the most current information. That instruction matters here because the festival and Thanksgiving openings depend on construction progress and will be set only days before each event.
A practical routine is to check the Easton Airport NOTAM during initial trip planning, again the day before departure, and once more on the morning of the flight. When a trip depends on a temporary reopening, add a calendar reminder for the 7 day announcement window so a missed update does not strand a plan.
What 2027 Holds for Runway 4/22
After the December 18 reopening, Runway 4/22 will remain open until approximately February 2027, when it will close again for several months. The airport asks travelers to plan for significant closures to Runway 4/22 through 2027.
That sequence means the current seven week closure is the first stage of a longer program rather than a single winter project. Pilots who base aircraft at Easton or visit regularly should keep a 2027 planning note that assumes further Runway 4/22 outages and continued reliance on Runway 15/33 during those periods.
| If you… | What to do |
|---|---|
| Plan to land or depart at Easton from October 29 to December 18 | Brief Runway 15/33 operations and verify the active runway in the current NOTAM. |
| Hope to use Runway 4/22 during the Waterfowl Festival or Thanksgiving weekend | Wait for the airport timing update at least 7 days before the event, then recheck the NOTAM. |
| Meet a passenger or schedule ground transport at the airport | Confirm arrival timing on the day of travel since traffic will use a single runway pattern. |
| Keep an aircraft at Easton or visit through 2027 | Keep Runway 15/33 as the backup plan and watch for the February 2027 closure notice. |
October 29, 2026, is the action gate. From that morning, file and brief every Easton trip for Runway 15/33 until the December reopening, except for announced event openings.
Early November is the festival gate. Do not book a festival arrival on Runway 4/22 until the airport posts the coordinated dates and times at least 7 days ahead.
December 18, 2026, is the restoration gate. After the morning reopening, confirm the runway is back in the NOTAM before resuming normal Runway 4/22 planning, and keep the February 2027 closure on the calendar.
Is Easton Airport closed from October 29 to December 18?
No. Only Runway 4/22 is closed during that period, while Runway 15/33 remains available for normal operations.
Will Runway 4/22 open for the Waterfowl Festival?
Yes, the airport plans to open Runway 4/22 for the Waterfowl Festival from November 13 to 15 and for Thanksgiving weekend, with exact dates and times announced at least 7 days in advance.
Where do I check current Easton Airport runway status?
Check the current NOTAMs for Easton Airport before every flight, since the airport points pilots to NOTAMs for the most current information during construction.
Will there be more Runway 4/22 closures after December?
Yes. The airport says Runway 4/22 will stay open after December 18 until approximately February 2027, then close again for several months, with significant closures expected through 2027.